TB MC Qu. 21-94 (Algo) A job was budgeted to require... job was budgeted to require 4 hours of labor per unit at $11.00 per
TB MC Qu. 21-94 (Algo) A job was budgeted to require... job was budgeted to require 4 hours of labor per unit at $11.00 per hour. The job consisted of 7,000 units and was completed in 24,000 hours at a total labor cost of $312,900. What is the otal direct labor variance? Multiple Choice $7,193 unfavorable. $7,000 unfavorable. $1,225 unfavorable. $2,293 unfavorables. $4,900 unfavorable