(TCO 4) An example of resource leveling would be(Points : 5) fast tracking a project to finish early. crashing a project to meet a critical
(TCO 4) An example of resource leveling would be(Points : 5) |
crashing a project to meet a critical deadline.
ensuring resource usage is balanced.
removing work from a project to compress its schedule