Question

1 Approved Answer

Test Name: Start - a , b , c , d , e , f , g , h , Finish Duration: 0 days, 1

Test Name: Start - a, b, c, d, e, f, g, h, Finish
Duration: 0 days, 10.67 days?, 12.17 days?, 12.33 days?, 6 days?, 14.33 days?, 9.67 days?, 10.33 days?, 7.83 days? 0 days
Optimistic Duration: 0 days, 8 days, 11 days, 7 days, 6 days, 10 days, 8 days, 5 days, 4 days, 0 days
Expected Duration: 0 days, 10 days, 12 days, 12 days, 6 days, 14 days, 10 days, 10 days, 8 days, 0 days
Pessimistic Duration: 0 days, 16 days, 14 days, 19 days, 6 days, 20 days, 10 days, 17 days, 11 days, 0 days
Predecessors: 1,2,3,3,3,4,5,5,6,8,7,9
Project Model using MS Project
Given the project model above, and the simulation data table on the next page:
Calculate and identify the:
a) median duration
b) mean duration
c) probability of completing the project in less than 50 days
d) critical index for each activity
e) critical index for each path

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management in the Supply Chain Decisions and Cases

Authors: Roger Schroeder, M. Johnny Rungtusanatham, Susan Goldstein

6th edition

73525243, 978-0073525242

More Books

Students also viewed these General Management questions

Question

What is the internal rate of return method? Discuss.

Answered: 1 week ago