The ACBA Company was awarded a contract valued at $2800000 few months ago. The project duration or delivery period was agreed to be no more
The ACBA Company was awarded a contract valued at $2800000 few months ago. The project duration or delivery period was agreed to be no more than 8 months based on one scrum team of three people. The project has been going on for 5 months (five sprints) and only 500 story points have been delivered successfully. If the total planned story points is given to be 1000, and assuming no changes in the scope or story points, what is the new estimated budget for this project