The Ace Machine Company is considering using a priority scheduling rule in its fabrication shop and must decide whether to use: the critical rule, the
The Ace Machine Company is considering using a priority scheduling rule in its fabrication shop and must decide
whether to use: the critical rule, the order slack rule, the shortest operation next rule or the slack per operation rule.
The table below shows the companys current inventory and shop status.
Exhibit
Order number
Manufacturing
Lead Time
Remaining
Time Remaining
Until Due Date
Current
Operation
Processing Time
Number of
Operations
Remaining
Total Processing
Time Remaining
Note: Time is measured in days. Manufacturing lead time remaining includes both the machine processing time and the length of time orders
spend moving and waiting to be processed in a machine queue. Current operating processing time as well as total processing time remaining
includes no move or queue times.
a State the formula for calculating the priority index for each of sequencing rules given above.
b Compute the scheduling priority index for each order in Exhibit for the four sequencing rules.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started