The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the
The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,600 units per 40-hour workweek. Performance Time (seconds) 20 This exercise only contains parts b, c, d, e, and f b) Given the demand, the cycle time for the production of the new train set = Task A seconds (round your response to one decimal place) 30 15 14 10 27 Predecessors A A A B. C D.