The activities needed to develop a new software application are listed in the following table with the activity times and their order in which the
The activities needed to develop a new software application are listed in the following table with the activity times and their order in which the activities need to be performed:
Activity | Duration (weeks) | Immediate Predecessor(s) |
---|---|---|
A | 3 | - |
B | 6 | A |
C | 9 | A |
D | 11 | A |
E | 5 | A |
F | 12 | B,C |
G | 11 | D,E |
H | 3 | F,G |
What is the overall duration of the project (in weeks)? weeks What is the earliest week you could start activity H? (Write the week number in the field below.) What is the earliest week you could finish activity F? What is the latest week you could start activity A? What is the latest week you could finish activity C? What is the slack time for activity C? weeks What would be the overall duration of the project if activity E were increased by 3weeks, from 5to 8weeks? weeks What would be the overall duration of the project if activity Fwere increased by 2weeks, from 12to 14weeks? weeks
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started