Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The activities needed to develop a new software application are listed in the following table with the activity times and the order in which the

The activities needed to develop a new software application are listed in the following table with the activity times and the order in which the activities need to be performed:

ActivityDuration (weeks)Immediate Predecessor(s)
A5-
B8A
C5A
D7A
E5A
F8B,C
G13D,E
H7F,G


What is the overall duration of the project (in weeks)?


What is the earliest week you could start activity F? (Write the week number in the field below.)

What is the earliest week you could finish activity G?

What is the latest week you could start activity B?

What is the latest week you could finish activity A?

What is the slack time for activity D?

What would be the overall duration of the project if activity F were increased by 3 weeks, from 8 to 11 weeks?

What would be the overall duration of the project if activity B were increased by 4 weeks, from 8 to 12 weeks?

Step by Step Solution

3.47 Rating (154 Votes )

There are 3 Steps involved in it

Step: 1

1 The overall duration of the project in weeks can be found by identifying the critical path which is the longest path of activities from start to finish The duration of the critical path is the overa... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Managing Global Supply Chains

Authors: Ray R. Venkataraman, Jeffrey K. Pinto

1st edition

1506302935, 1506302939, 978-1506302935

More Books

Students also viewed these General Management questions