The following table shows the time information for the activities needed to develop an ad campaign. 1.

Question:

The following table shows the time information for the activities needed to develop an ad campaign.
1. Calculate the expected activity times (round to nearest integer).

2. Calculate the slack for each activity. What is the project€™s total length? Make sure you fully label all nodes in the network.

3. Identify the critical path. What are the alternative paths, and how much slack time is associated with each feeder path?

4. Identify the burst activities and merge activities.

5. Given the activity variances, what is the likelihood of finishing the project on week 24?

6. Suppose you want to be 99% sure the project will finish on time. How many additional weeks would your project team need to ensure this likelihood?

Time Estimates (week) Immediate Predecessor(s) Activity Optimistic Most Likely Pessimistic A 1 4 10 3 A 13 14 A, C 14 6.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Managing Global Supply Chains

ISBN: 978-1506302935

1st edition

Authors: Ray R. Venkataraman, Jeffrey K. Pinto

Question Posted: