You have a project with the following information: 1. Calculate each activitys expected duration (TE) and variance.

Question:

You have a project with the following information:

Time Estimates (week) Immediate Predecessor(s) Activity Optimistic Most Likely Pessimistic 4 1 3 3 13 14 A 3 6. 12 A, C


1. Calculate each activity€™s expected duration (TE) and variance. Which activities have the greatest variance?
2. Create a network for this project. What is the expected duration?
3. What is the expected duration if we require a probability of 90% that the project will be completed on time?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Managing Global Supply Chains

ISBN: 978-1506302935

1st edition

Authors: Ray R. Venkataraman, Jeffrey K. Pinto

Question Posted: