The activities that need to be crashed should be the activities in the critical path. Therefore, we need to look at the activities C-A-B. Based
The activities that need to be crashed should be the activities in the critical path. Therefore, we need to look at the activities C-A-B. Based on C-A-B, the lowest crash cost per week is activity B with only $1000/week crash cost