The actual hourly rate paid above or below the standard hourly rate, multiplied by the actual number of hours worked is the: a.Labor rate variance.

The actual hourly rate paid above or below the standard hourly rate, multiplied by the actual number of hours worked is the: a.Labor rate variance. b.Labor efficiency variance. c.Labor usage variance. d.Labor direct variance.

Step by Step Solution

3.40 Rating (147 Votes )

There are 3 Steps involved in it

Step: 1

Answer Option a Labor rate variance Labor rate variance is calculated a... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Applied Statistics In Business And Economics

Authors: David Doane, Lori Seward

4th Edition

73521485, 978-0073521480

More Books

Students also viewed these Accounting questions