Question

1 Approved Answer

The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given in

The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given in the following table. Indirect project costs amount to

$150

per day. The company will incur a

$200

per day penalty for each day the project lasts beyond day

15.

Activity Normal Time(days) Normal Cost ($) Crash Time(days)

Crash Cost

($)

Immediate Predecessor(s)
A 4 900 3 1,000
B 6 1,000 3 2,200
C 4 500 3 1,000 A, B
D 3 1,200 2 1,500 B
E 4 1,500 4 1,500 C, D
F 2 1,300 1 1,400 E
G 4 900 1 1,500 E
H 5 300 2 600 G

Part 2

a. What is the project's duration if only normal times are used?

The project duration is

enter your response here

day(s). (Enter your response as an integer.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Inventory Optimization Models And Simulations

Authors: Nicolas Vandeput

1st Edition

3110673916, 978-3110673913

More Books

Students also viewed these General Management questions