Question

1 Approved Answer

The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given in

The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given in the following table. - Indirect project costs amount to $150 per day. The company will incur a $100 per day penalty for each day the project lasts beyond day 15.
\table[[Activity,\table[[Normal],[Time (days)]],Normal Cost ($),\table[[Crash],[Time (days)]],\table[[Crash Cost],[($)]],Immediate Predecessor(s)],[A,6,800,4,1,200,-],[B,6,1,000,2,2,200,-],[C,2,600,1,900,A, B],[D,4,1,200,2,2,000,B],[E,4,1,000,1,1,300,C, D],[F,3,1,300,1,1,400,E],[G,3,900,3,900,E],[H,5,500,3,900,G]]
a. What is the project's duration if only normal times are used?
The project duration is day(s).(Enter your response as an integer.)
b. What is the minimu-cost schedule?
With the minimum-cost schedule, the project duration is day(s).(Enter your response as an integer.)
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam

11th Edition

978-0324651812, 324651813, 978-0324651751

More Books

Students also viewed these General Management questions