Question

1 Approved Answer

The analogous estimating technique relies on: Question 17 options: The estimator having relevant experience on creating estimates for similar project(s) Industry-established formulas that are based

The analogous estimating technique relies on: Question 17 options: The estimator having relevant experience on creating estimates for similar project(s) Industry-established formulas that are based upon averages from similar projects. The fact that the project boundaries are clear and achievable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management For Business And Engineering Principles And Practice

Authors: John M. Nicholas

2nd Edition

0750678240, 9780750678247

More Books

Students also viewed these General Management questions

Question

If you are a guest, what dining etiquette should you follow?

Answered: 1 week ago

Question

What are the key differences?

Answered: 1 week ago