The attempt to recognize and manage potential and unforeseen trouble spots that may occur when a project is implemented is known as Multiple Choice scenario
The attempt to recognize and manage potential and unforeseen trouble spots that may occur when a project is implemented is known as
Multiple Choice
scenario analysis.
risk management.
disaster protection.
risk forecasting.
contingency planning.