Question

1 Approved Answer

The BEST way to present the project schedule to senior management is to display a __________. Select one: a. Schedule baseline b. Bar chart c.

The BEST way to present the project schedule to senior management is to display a __________. Select one: a. Schedule baseline b. Bar chart c. Work breakdown structure d. Schedule network diagram