Question
The BHI Project Evaluation The Sawmill Spreadsheet was a relatively simple case to get you started on evaluation. Now, we will move on to a
The BHI Project Evaluation
The Sawmill Spreadsheet was a relatively simple case to get you started on evaluation. Now, we will move on to a typical case study that you might be asked to prepare in a firm.
As a business manager for your firm, Global Biotechnology, you have a new process for Biosynthetic Human Insulin (BHI) in development. Since you are in the position of business evaluation for Global, you will be assigned to "take a look" at this job and see if it's a good project. To evaluate the BHI Project, a spreadsheet analysis will be required. Since this project is just now coming to a point of evaluation in R&D, there is not much to go on. Note that you must distinguish between assumptions that you, the business evaluator, must make from those items of information that you would be required to obtain from others to create a defensible recommendation. Since time is of the essence, you will need to decide which items of information are more important than others.
R&D has just issued their report on the new Biosynthetic Human Insulin process and plant. They have recommended that Global Biotechnology pursue this project immediately as it appears to have a high return. The preliminary flowsheet has been developed and a first pass capital cost estimate has been issued with the recommendation that Global spend $122 million on the new facility. As business manager you have been asked to evaluate this project and make a recommendation to senior management.
Here is the key data (and the only data) in the research division report:
Estimated Direct Fixed Capital-$122 million
Estimated Initial working capital-$8 million
Required Plant capacity at 100%-1500Kg/yr
Estimated BHI unit production cost-$41/gram
Estimated BHI selling price-$110/gram
BHI project return -greater than 35%
There is not much to go on here. You will have to start by making appropriate evaluation assumptions.
Some important areas that drive evaluations are:
1) Project life
2) Tax life of the assets
3) Corporate tax rate
4) Inflation rate for costs/prices
5) Proportion of fixed cost/variable cost in $41/gram
6) Length of time to build the plant and spending curve (expenditures per year)
Although there are many possible evaluation assumptions you can select. For your work to proceed, and to create a common base case, you will use these base case assumptions:
1) Project life-3 years for capital construction, and 15 years of operations for a total scenario of 18 years.
2) Tax life of the assets-composite average 10 years MACRS class.
3) Corporate tax rate-35%.
4) Inflation for all costs/prices-3%.
5) Proportion of fixed to variable cost-75% fixed, 25% variable.
6) Length of time to build-3 years, capex - 30%, 40%, 30%.
7) The sales rate, which is the plant capacity utilization in the initial operating years. You will use 50% of capacity year 1, 75% of capacity year 2 and 100% of capacity in year 3.
The initial working capital is the cost of the initial charge of raw materials and work in process supplies, plus the funding of accounts receivable until cash receipts from sales are received. The $8 million is deducted from the first operating year after tax cashflow and is recovered at the end of the project life.
Remember to build your spreadsheet with formulas for relevant variables so that if you change assumptions you can let the spreadsheet do the computational work.
One last comment about these assumptions: In business, important decisions are made everyday with incorrect and incomplete information. The issue we face is how accurate does our information and resulting assumptions have to be to make correct decisions. Decisions MUST be made on a timely basis. If we wait for all the information to be known, then the decision is history before it is made. Also, we should always be evaluating our assumptions and be prepared to make appropriate corrections as they become necessary.
Adding the answers, but I need to know how to find NPV @30%, 25%, 20%, and 15%
Direct fixed capital Initial working capital Plant capacity production cost / unit selling price / unit $122 $8 1500000 g/yr 41 BHI Project First Pass Base Case Other Assumptions and Notes: All dollars shown in millions $/g 110 Sig Capital exp (yr 1) 30% Capital exp (yr 2) 40% 30% 35% 3% Capital exp (yr 3) Tax rate Inflation rate fixed portion variable portion capacity (yr 1) capacity (yr 2) 75% 25% 50% 75% capacity (yr 3 onwards) 100% Tax lif of the assets-composite average 10 years MACRS class MACRS factors 0.1 Year 0.18 0.144 0.1152 0.0922 0.0737 0.0655 0.0655 0.0655 0.0655 0.0329 4 5 6 7 8 9 10 11 12 13 14 15 100% 100% 100% 16 0 1 2 3 0% 0% 17 Production Level 0% 50% 75% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% Construction cost/year (30%,40%,30% inflated) $37 $50 $39 Revenue $273 Cash Expense $90 $139 $191 $197 $203 $209 $215 $59 $65 $71 $73 $76 $78 $80 $8 $8 $8 $8 $8 $8 $222 $228 $83 $85 $8 $235 $88 $8 $242 $250 $257 $265 $90 $93 $96 $99 $8 $8 $8 $8 $102 Book Depreciation $8 $8 $8 Book Income Pre-Tax $123 $127 $131 $135 $163 $23 $66 $112 $115 $119 $8 $23 $39 $40 $15 $43 $73 $75 $77 $139 $49 Book Tax @ 35% $42 $43 $44 $46 $47 $144 $148 $153 $158 $55 $93 $98 $99 $103 $50 $52 $54 $57 After Tax Income $80 $82 $85 $88 $90 $106 Financial Measures Profit Margin 17% 31% 38% 38% 38% 39% 30% 30% 39% 39% 38% 38% 3.8% $92 $84 $75 $67 81% 92% 106% 123% 145% $34 $25 $17 38% 38% $50 $50 $42 174% 216% Net Assets ROA% $8 $37 $87 $126 $117 $109 $101 13% 39% 72% $0 279% 383% 593% 1223% n/a Cashflow Revenue $90 $139 $191 $197 $203 $209 $265 $273 $76 $78 $102 Cash Expense Tax Depreciation Pre-Tax Income Tax @ 35% After Tax Income $59 $65 $71 $73 $13 $23 $18 $14 $12 $19 $52 $102 $109 $116 $122 $0 $215 $222 $228 $235 $80 $83 $85 $88 $9 $8 $8 $8 $8 $135 $139 $47 $49 $88 $91 $242 $250 $257 $90 $93 $96 $99 $4 $0 SO SO $148 $157 $161 $166 $52 $55 $56 $127 $131 $171 $58 $60 $7 $18 $36 $38 $40 $12 $34 $66 $71 $75 $43 $79 $44 $46 $82 $85 $96 $102 $105 $108 $111 Working Capital ($8) $8 After Tax Cashflow Cummulative Cashflow ($37) ($50) ($39) $17 $56 $84 ($37) (587) ($126) ($109) (553) $32 $85 $87 $88 $117 $204 $292 $91 $93 $96 $99 $383 $476 $572 $671 $100 $102 $105 $108 $119 $771 $873 $978 $1,086 $1,205 Payback period (yr.) 2.6 $3 NPV @ 35% NPV @ 30% $23 NPV @ 25% $56 NPV @ 20% $109 NPV @ 15% $198 IRR PV Index (15%) 35.8% 1.6
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started