Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The blue curve (labeled L) depicts the NPV for a project with larger cash flows later of -$1,000, $100, $300, $400, and $675. The red

image text in transcribedimage text in transcribedimage text in transcribed

The blue curve (labeled "L") depicts the NPV for a project with larger cash flows later of -$1,000, $100, $300, $400, and $675. The red curve (labeled "S") depicts the NPV for a project with larger cash flows sooner of -$1,000, $500, $400, $300, and $100. Drag on the graph either left or right to change the cost of capital interest rate at which the NPV is evaluated for the two projects. $500 (1+0.1000)! $400 (1+0.1000) $300 (1+0.1000)3 $100 (1+0.1000)4 Project S: NP V = CFo + E1 d+rF CF, = -$1,000 = $78.82 Project L: NPV = CFo+EN CF, 2t=1 (1+r) $300 (1+0.1000)- $400 (1+0.1000)* T (1+0.1000)* $100 (1+0.1000)! $675 = -$1,000 + = $100.40 NPV ($) 500 L. 400 - 300 200 100.40100 78.82 10 20 -100 10 Cost of Capital (%) 1. What is the approximate cost of capital for which the two cash flows are about equal? a. 10% b. 12% c. 13.5% d. 14.5% -Select- 2. What is the approximate internal rate of return (IRR) for the Project L cash flow? a. 10% b. 12% c. 13.5% d. 14.5% -Select- 3. What is the approximate internal rate of return (IRR) for the Project S cash flow? a. 10% b. 12% c. 13.5% d. 14.5% -Select- 4. What is the name for the point at which the two projects' NPVS are equal? a. Inflection point b. Equal NPV rate c. Crossover rate d. There is no special name for this point -Select- 5. At a cost of capital less than the point at which they cross, which project will have the higher NPV? a. Project S b. Project L c. Project S and L will have the same NPV d. Cannot determine -Select- 6. At a cost of capital greater than the point at which they cross, which project will have the higher NPV? a. Project S b. Project L c. Project S and L will have the same NPV d. Cannot determine -Select- 7. The internal rate of return (IRR) is the point at which a project's NPV equals 0. If the cost of capital were 5% (move the slider so that is the case), then a. Project S is the better project because it has the higher IRR. b. Project L is the better project because it has the higher NPV. c. It depends because there is a conflict between IRR and NPV. -Select- 8. If the cost of capital was greater than the point at which the two projected NPVS are equal, then a. It depends because there is a conflict between IRR and NPV. b. There is no conflict because Project S has both a higher NPV and a higher IRR than Project L. c. There is no conflict because Project L has both a higher NPV and a higher IRR than Project S. -Select- The blue curve (labeled "L") depicts the NPV for a project with larger cash flows later of -$1,000, $100, $300, $400, and $675. The red curve (labeled "S") depicts the NPV for a project with larger cash flows sooner of -$1,000, $500, $400, $300, and $100. Drag on the graph either left or right to change the cost of capital interest rate at which the NPV is evaluated for the two projects. $500 (1+0.1000)! $400 (1+0.1000) $300 (1+0.1000)3 $100 (1+0.1000)4 Project S: NP V = CFo + E1 d+rF CF, = -$1,000 = $78.82 Project L: NPV = CFo+EN CF, 2t=1 (1+r) $300 (1+0.1000)- $400 (1+0.1000)* T (1+0.1000)* $100 (1+0.1000)! $675 = -$1,000 + = $100.40 NPV ($) 500 L. 400 - 300 200 100.40100 78.82 10 20 -100 10 Cost of Capital (%) 1. What is the approximate cost of capital for which the two cash flows are about equal? a. 10% b. 12% c. 13.5% d. 14.5% -Select- 2. What is the approximate internal rate of return (IRR) for the Project L cash flow? a. 10% b. 12% c. 13.5% d. 14.5% -Select- 3. What is the approximate internal rate of return (IRR) for the Project S cash flow? a. 10% b. 12% c. 13.5% d. 14.5% -Select- 4. What is the name for the point at which the two projects' NPVS are equal? a. Inflection point b. Equal NPV rate c. Crossover rate d. There is no special name for this point -Select- 5. At a cost of capital less than the point at which they cross, which project will have the higher NPV? a. Project S b. Project L c. Project S and L will have the same NPV d. Cannot determine -Select- 6. At a cost of capital greater than the point at which they cross, which project will have the higher NPV? a. Project S b. Project L c. Project S and L will have the same NPV d. Cannot determine -Select- 7. The internal rate of return (IRR) is the point at which a project's NPV equals 0. If the cost of capital were 5% (move the slider so that is the case), then a. Project S is the better project because it has the higher IRR. b. Project L is the better project because it has the higher NPV. c. It depends because there is a conflict between IRR and NPV. -Select- 8. If the cost of capital was greater than the point at which the two projected NPVS are equal, then a. It depends because there is a conflict between IRR and NPV. b. There is no conflict because Project S has both a higher NPV and a higher IRR than Project L. c. There is no conflict because Project L has both a higher NPV and a higher IRR than Project S. -Select

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Mergers Acquisition And Other Restructuring Activities

Authors: Donald M. Depamphilis

6th Edition

123854857, 978-0123854858

More Books

Students also viewed these Finance questions