Question
The board of directors for Apache Construction Corp. is meeting to choose between the completed-contract method and the percentage-of-completion method of accounting for long-term contracts
The board of directors for Apache Construction Corp. is meeting to choose between the completed-contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Apache's controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information:
Apache commenced doing business on January 1, 2020.
Construction activities for the year ended December 31, 2020, were as follows:
Project
Total contract
Price
Billings through
12/31/20
Cash collections through
12/31/20
A
$ 615,000
$ 340,000
$ 310,000
B
450,000
135,000
135,000
C
475,000
475,000
390,000
D
600,000
240,000
160,000
E
480,000
400,000
400,000
$ 2,620,000
$ 1,590,000
$ 1,395,000
Project
Contract costs incurred through 12/31/20
Estimated additional costs to complete contracts
A
$ 510,000
$ 120,000
B
130,000
260,000
C
350,000
-0-
D
370,000
290,000
E
320,000
80,000
$ 1,680,000
$ 750,000
Each contract is with a different customer.
Any work remaining to be done on the contracts is expected to be completed in 2021.
Required
1.schedule by project, calculating the amount of gross profit (or loss) for the 2020 calendar year, which would be reported under:
a.The completed-contract method.
b.The percentage-of-completion method (based on estimated costs).
2.Prepare the general journal entry to record revenue and gross profit on project B for 2020, assuming that the percentage-of-completion method is used.
3.Indicate the balances that would appear in the statement of financial position at December 31, 2020 for the following accounts for Project D, assuming that the percentage-of-completion method is used.
a.Accounts Receivable
b.Billings on Construction in Process
c.Construction in Process
How would the balances in the accounts discussed in part 3 above change (if at all) for Project D, if the completed-contract method is used?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started