The bottleneck station in a factory has preventive maintenance performed on a regular schedule. Its natural process rate is 3 jobs per hour with a
The bottleneck station in a factory has preventive maintenance performed on a regular schedule. Its natural process rate is 3 jobs per hour with a CV of 0.75. The maintenance is done after 100 jobs, and it takes 2.5 hours with a CV of 1.25.
1. What is the effective process time and its CV? 2.Assume there are 2 servers at the station. What is the bottleneck rate?