Question

1 Approved Answer

The bottom-up estimating technique: (More than one answer is correct, could be 2, could be all) a) is used to get accurate estimate of the

The bottom-up estimating technique:

(More than one answer is correct, could be 2, could be all)

a) is used to get accurate estimate of the resources required for each project activity when there is no reliable data available.

b) only takes project dependencies into consideration.

c) takes into consideration the cost of the resources needed for each project activity.

d) takes into consideration the skills required for the project activities.

e) takes into consideration the time duration of the project activities.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Applied Statistics From Bivariate Through Multivariate Techniques

Authors: Rebecca M. Warner

2nd Edition

141299134X, 978-1412991346

Students also viewed these General Management questions

Question

differentiate between good and bad ways of working hard;

Answered: 1 week ago