Question
The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each project has an initial after-tax cash outflow of $7,000 and has an expected
The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each project has an initial after-tax cash outflow of $7,000 and has an expected life of 3 years. Annual project after-tax cash flows begin 1 year after the initial investment and are subject to the following probability distributions:
Project A Project B
Probability Cash Flows Probability Cash Flows
0.2 $6,250 0.2 $ 0
0.6 7,000 0.6 7,000
0.2 7,750 0.2 18,000
BPC has decided to evaluate the riskier project at 11% and the less-risky project at 8%.
What is each project's expected annual after-tax cash flow? Round your answers to the nearest cent.
Project A: $_____ Project B: $____
Project B's standard deviation (B) is $5,776 and its coefficient of variation (CVB) is 0.74. What are the values of A and CVA? Do not round intermediate calculations. Round your answer for standard deviation to the nearest cent and for coefficient of variation to two decimal places.
A: $_______ CVA:_____
Based on the risk-adjusted NPVs, which project should BPC choose? Project B If you knew that Project B's cash flows were negatively correlated with the firm's other cash flows, but Project A's cash flows were positively correlated, how might this affect the decision?
If Project B's cash flows were negatively correlated with gross domestic product (GDP), while A's cash flows were positively correlated, would that influence your risk assessment? .
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started