Question
THE CAPITAL ASSET PRICING MODEL ASSUMES INVESTORS ARE REWARDED FOR BEARING _________ RISK. UNDIVERSIFIABLE FIRM-SPECIFIC DIVERSIFIABLE UNSYSTEMATIC CONSIDER THE CASH FLOWS FOR PROJECT Y SHOWN
-
THE CAPITAL ASSET PRICING MODEL ASSUMES INVESTORS ARE REWARDED FOR BEARING _________ RISK.
UNDIVERSIFIABLE
FIRM-SPECIFIC
DIVERSIFIABLE
UNSYSTEMATIC
-
CONSIDER THE CASH FLOWS FOR PROJECT Y SHOWN IN THE FOLLOWING TABLE:
TIME PROJECT Y 0 -$500,000 1 $300,000 2 $300,000 3 $300,000 4 $300,000 5 $200,000
GIVEN A REQUIRED RETURN (AKA DISCOUNT RATE) OF 10%, THE PROFITABILITY INDEX FOR PROJECT Y IS ______. ACCORDING TO THE PROFITABILITY INDEX DECISION RULE THE PROJECT _________ BE ACCEPTED.
.75; SHOULD NOT
2.15; SHOULD
.58; SHOULD NOT
1.15; SHOULD
-
CONSIDER THE FOLLOWING INFORMATION FOR THE FIN 301 CORPORATION:
STATE OF ECONOMY PROBABILITY RETURN DEPRESSION .10
-25%
AVERAGE .80
12%
BOOM .10
30%
FIN 301'S EXPECTED RETURN IS _______ AND ITS STANDARD DEVATION IS _______ AND ITS COEFFICIENT OF VARIATION IS ________. 10.1%; 13.85%; 1.37%
10.1%; 165.64%; 16.4%
10.1%; 12.87%; 1.27
10.1%; 11.29%; 1.12%
-
CONSIDER THE FOLLOWING STOCK RETURN INFORMATION FOR THE MARKET PORTFOLIO AND FOR THE FIN 301 CORPORATION:
YEAR CHANGE IN MARKET RETURN
CHANGE IN FIN 301 STOCK RETURN
2013
10
12
2012
8
12
2011
2
6
2010
-7
-12
2009
5
2
2008
19
30
2007
4
-2
2006
23
36
2005
-15
-28
2004
-6
-1
IF THE RISK-FREE RATE IS 4% AND THE MARKET RISK PREMIUM IS 6%, THEN THE REQUIRED RETURN ON FIN 301 COMMON STOCK WOULD BE _________.
13.30%
11.95%
10.35%
12.75%
-
THE SLOPE OF THE SECURITY MARKET LINE JUST ROSE. THIS MUST MEAN________
SYSTEMATIC RISK JUST ROSE
INVESTORS JUST BECOME MORE RISK-AVERSE.
UNSYSTEMATIC RISK JUST ROSE.
INVESTORS EXPECT THE INFLATION RATE TO INCREASE.
-
CAPITAL BUDGETING PROJECTS A AND B ARE MUTUALLY EXCLUSIVE. AT A DISCOUNT RATE OF 0%, THE NPV OF PROJECT A EXCEEDS THAT OF PROJECT B. HOWEVER, THE IRR OF PROJECT B EXCEEDS THAT OF PROJECT A. USING ONLY THIS INFORMATION, WE CAN CONCLUDE _________.
I. PROJECT A SHOULD BE SELECTED II. PROJECT B SHOULD BE SELECTED III. THE NPV PROFILES OF PROJECTS A AND B CROSS IV. THE NPV PROFILES OF PROJECTS A AND B DO NOT CROSS
II AND IV
IV ONLY
I AND III
III ONLY
-
CONSIDER THE FOLLOWING INFORMATION:
SECURITY BETA REQUIRED RETURN RISK-FREE RATE 0
4%
MARKET PORTFOLIO 1
10%
FIN 301 1.5
?
ACCORDING TO THE CAPITAL ASSET PRICING MODEL, THE REQUIRED RETURN FOR FIN 301 IS ________
10%
14.5%
16%
13%
-
BETA MEASURES A SECURITY'S _________
SYSTEMATIC RISK
FIRM-SPECIFIC RISK
UNSYSTEMATIC RISK
DIVERSIFIABLE RISK
-
THE JSU CORPORATION HAS A BETA OF 1.5. THIS MEANS THAT IF THE MARKET RETURN FALLS BY 6%, JSU'S RETURN SHOULD ______.
FALL BY 9%
FALL BY 10.5%
RISE BY 12%
RISE BY 9%
-
YOU LEARN THE H1N1 VIRUS HAS MUTATED INTO A FAR MORE VIRULENT FORM AND THERE IS NO KNOWN VACCINE OR CURE. ONE THIRD FOR THE WORLD'S POPULATION IS EXPECTED TO DIE FROM THE VIRUS. BASED ON THIS INFORMATION WE WOULD EXPECT _____________.
NO CHANGE IN THE SECURITY MARKET LINE.
THE SECURITY MARKET LINE TO SHIFT UP AND TO THE LEFT.
THE SLOPE OF THE SECURITY MARKET LINE TO STEEPEN.
THE SECURITY MARKET LINE TO SHIFT DOWN AND TO THE RIGHT.
-
YOU OBSERVE A SECURITY'S TOTAL RISK INCREASED BUT ITS BETA IS UNCHANGED. THIS MUST MEAN ITS ________ RISK JUST ROSE.
UNSYSTEMATIC
SYSTEMATIC
MARKET
UNDIVERSIFIABLE
-
THE STANDARD DEVIATION OF A SECURITY'S RETURNS IS A MEASURE OF ITS
TOTAL RISK
SYSTEMATIC RISK
UNSYSTEMATIC RISK
MARKET RISK
-
CONSIDER THE CASH FLOWS FOR PROJECT Y SHOWN IN THE FOLLOWING TABLE:
TIME PROJECT Y 0 -$500,000 1 $300,000 2 $300,000 3 $300,000 4 $300,000 5 $200,000
THE PAYBACK PERIOD FOR PROJECT Y IS _________. IF MANAGEMENT'S MAXIMUM ALLOWABLE PAYBACK PERIOD IS 3 YEARS, THEN ACCORDING TO THE PAYBACK DECISION RULE THE PROJECT _______ BE ACCEPTED.
2.35; SHOULD
3.50; SHOULD NOT
3.72; SHOULD NOT
1.67; SHOULD
THE CAPITAL ASSET PRICING MODEL ASSUMES INVESTORS ARE REWARDED FOR BEARING _________ RISK.
UNDIVERSIFIABLE | ||
FIRM-SPECIFIC | ||
DIVERSIFIABLE | ||
UNSYSTEMATIC |
CONSIDER THE CASH FLOWS FOR PROJECT Y SHOWN IN THE FOLLOWING TABLE:
TIME | PROJECT Y |
0 | -$500,000 |
1 | $300,000 |
2 | $300,000 |
3 | $300,000 |
4 | $300,000 |
5 | $200,000 |
GIVEN A REQUIRED RETURN (AKA DISCOUNT RATE) OF 10%, THE PROFITABILITY INDEX FOR PROJECT Y IS ______. ACCORDING TO THE PROFITABILITY INDEX DECISION RULE THE PROJECT _________ BE ACCEPTED.
.75; SHOULD NOT | ||
2.15; SHOULD | ||
.58; SHOULD NOT | ||
1.15; SHOULD |
CONSIDER THE FOLLOWING INFORMATION FOR THE FIN 301 CORPORATION:
STATE OF ECONOMY | PROBABILITY | RETURN |
DEPRESSION | .10 | -25% |
AVERAGE | .80 | 12% |
BOOM | .10 | 30% |
FIN 301'S EXPECTED RETURN IS _______ AND ITS STANDARD DEVATION IS _______ AND ITS COEFFICIENT OF VARIATION IS ________.
10.1%; 13.85%; 1.37% | ||
10.1%; 165.64%; 16.4% | ||
10.1%; 12.87%; 1.27 | ||
10.1%; 11.29%; 1.12% |
CONSIDER THE FOLLOWING STOCK RETURN INFORMATION FOR THE MARKET PORTFOLIO AND FOR THE FIN 301 CORPORATION:
YEAR | CHANGE IN MARKET RETURN | CHANGE IN FIN 301 STOCK RETURN |
2013 | 10 | 12 |
2012 | 8 | 12 |
2011 | 2 | 6 |
2010 | -7 | -12 |
2009 | 5 | 2 |
2008 | 19 | 30 |
2007 | 4 | -2 |
2006 | 23 | 36 |
2005 | -15 | -28 |
2004 | -6 | -1 |
IF THE RISK-FREE RATE IS 4% AND THE MARKET RISK PREMIUM IS 6%, THEN THE REQUIRED RETURN ON FIN 301 COMMON STOCK WOULD BE _________.
13.30% | ||
11.95% | ||
10.35% | ||
12.75% |
THE SLOPE OF THE SECURITY MARKET LINE JUST ROSE. THIS MUST MEAN________
SYSTEMATIC RISK JUST ROSE | ||
INVESTORS JUST BECOME MORE RISK-AVERSE. | ||
UNSYSTEMATIC RISK JUST ROSE. | ||
INVESTORS EXPECT THE INFLATION RATE TO INCREASE. |
CAPITAL BUDGETING PROJECTS A AND B ARE MUTUALLY EXCLUSIVE. AT A DISCOUNT RATE OF 0%, THE NPV OF PROJECT A EXCEEDS THAT OF PROJECT B. HOWEVER, THE IRR OF PROJECT B EXCEEDS THAT OF PROJECT A. USING ONLY THIS INFORMATION, WE CAN CONCLUDE _________.
I. PROJECT A SHOULD BE SELECTED II. PROJECT B SHOULD BE SELECTED III. THE NPV PROFILES OF PROJECTS A AND B CROSS IV. THE NPV PROFILES OF PROJECTS A AND B DO NOT CROSS
II AND IV | ||
IV ONLY | ||
I AND III | ||
III ONLY |
CONSIDER THE FOLLOWING INFORMATION:
SECURITY | BETA | REQUIRED RETURN |
RISK-FREE RATE | 0 | 4% |
MARKET PORTFOLIO | 1 | 10% |
FIN 301 | 1.5 | ? |
ACCORDING TO THE CAPITAL ASSET PRICING MODEL, THE REQUIRED RETURN FOR FIN 301 IS ________
10% | ||
14.5% | ||
16% | ||
13% |
BETA MEASURES A SECURITY'S _________
SYSTEMATIC RISK | ||
FIRM-SPECIFIC RISK | ||
UNSYSTEMATIC RISK | ||
DIVERSIFIABLE RISK |
THE JSU CORPORATION HAS A BETA OF 1.5. THIS MEANS THAT IF THE MARKET RETURN FALLS BY 6%, JSU'S RETURN SHOULD ______.
FALL BY 9% | ||
FALL BY 10.5% | ||
RISE BY 12% | ||
RISE BY 9% |
YOU LEARN THE H1N1 VIRUS HAS MUTATED INTO A FAR MORE VIRULENT FORM AND THERE IS NO KNOWN VACCINE OR CURE. ONE THIRD FOR THE WORLD'S POPULATION IS EXPECTED TO DIE FROM THE VIRUS. BASED ON THIS INFORMATION WE WOULD EXPECT _____________.
NO CHANGE IN THE SECURITY MARKET LINE. | ||
THE SECURITY MARKET LINE TO SHIFT UP AND TO THE LEFT. | ||
THE SLOPE OF THE SECURITY MARKET LINE TO STEEPEN. | ||
THE SECURITY MARKET LINE TO SHIFT DOWN AND TO THE RIGHT. |
YOU OBSERVE A SECURITY'S TOTAL RISK INCREASED BUT ITS BETA IS UNCHANGED. THIS MUST MEAN ITS ________ RISK JUST ROSE.
UNSYSTEMATIC | ||
SYSTEMATIC | ||
MARKET | ||
UNDIVERSIFIABLE |
THE STANDARD DEVIATION OF A SECURITY'S RETURNS IS A MEASURE OF ITS
TOTAL RISK | ||
SYSTEMATIC RISK | ||
UNSYSTEMATIC RISK | ||
MARKET RISK |
CONSIDER THE CASH FLOWS FOR PROJECT Y SHOWN IN THE FOLLOWING TABLE:
TIME | PROJECT Y |
0 | -$500,000 |
1 | $300,000 |
2 | $300,000 |
3 | $300,000 |
4 | $300,000 |
5 | $200,000 |
THE PAYBACK PERIOD FOR PROJECT Y IS _________. IF MANAGEMENT'S MAXIMUM ALLOWABLE PAYBACK PERIOD IS 3 YEARS, THEN ACCORDING TO THE PAYBACK DECISION RULE THE PROJECT _______ BE ACCEPTED.
2.35; SHOULD | ||
3.50; SHOULD NOT | ||
3.72; SHOULD NOT | ||
1.67; SHOULD |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started