Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The Chinese government is considering three new flood control projects on the Huaihe River. Projects A and B consist of permanent dikes. Project C is

The Chinese government is considering three new flood control projects on the Huaihe River. Projects A and B consist of permanent dikes. Project C is a small dam. The dam will have recreation and irrigation benefits as well as the flood control benefits. Facts about the three projects are shown in the following table. Each project has a life of 28 years. The MARR is 10 percent.

Project A

Project B

Project C

First cost (millions of yuan)

207

251

422

Annual benefits (millions of yuan)

26.9

34.5

57.6

Annual operating and maintenance costs (millions of yuan)

2.5

2.5

4.2

Complete parts (a) through (d) below. Click the icon to view the table of compound interest factors for discrete compounding periods when

i=10%.

a. Use present worth to choose the best project. The present worths in millions of yuan for projects A, B, and C, respectively, are

enter your response here,

enter your response here, and

enter your response here. Project is the best choice. (Round to two decimal places as needed.) b. Compute the benefit-cost ratios for the three projects. The BCRs for projects A, B, and C, respectively, are

enter your response here,

enter your response here, and

enter your response here. (Round to three decimal places as needed.)

c. Use incremental benefitcost to choose the best project. BCR(BA) is

enter your response here, and BCR(CB) is

enter your response here, so project is the best choice. (Round to three decimal places as needed.) d. It is possible that the dam (project C) will cause some wildlife damage. This damage might be prevented by an additional expenditure of 23 million yuan when the dam is constructed. Does this change the choice of best project? Compute the

benefitcost ratio of project C assuming the extra 23 million yuan is an addition to the first cost. Use incremental benefitcost to choose the best project. BCR(C) is

enter your response here and BCR(CB) is

enter your response here, so project is the best choice.(Round to three decimal places as needed.)

image text in transcribed

The Chinese government is considering three new flood control projects on the Huaihe River. Projects A and B consist of permanent dikes. Project C is a small dam. The dam will have recreation and irrigation benefits as well as the flood control benefits. Facts about the three projects are shown in the following table. Each project has a life of 28 years. The MARR is 10 percent. First cost (millions of yuan) Annual benefits (millions of yuan) Annual operating and maintenance costs (millions of yuan) Complete parts (a) through (d) below. Project A 207 26.9 2.5 Project B 251 34.5 2.5 Project C 422 57.6 4.2 3 Click the icon to view the table of compound interest factors for discrete compounding periods when i = 10%. a. Use present worth to choose the best project. 1and Project is the best choice. The present worths in millions of yuan for projects A, B, and C, respectively, are (Round to two decimal places as needed.) b. Compute the benefit-cost ratios for the three projects. and The BCRs for projects A, B, and C, respectively, are (Round to three decimal places as needed.) c. Use incremental benefit-cost to choose the best project. BCR(B-A) is and BCR(C-B) is so project is the best choice. (Round to three decimal places as needed.) d. It is possible that the dam (project C) will cause some wildlife damage. This damage might be prevented by an additional expenditure of 23 million yuan when the dam is constructed. Does this change the choice of best project? Compute the benefit-cost ratio of project C assuming the extra 23 million yuan is an addition to the first cost. Use incremental benefit-cost to choose the best project. Vis the best choice. BCR(C) is and BCR(C-B) is so project (Round to three decimal places as needed.) The Chinese government is considering three new flood control projects on the Huaihe River. Projects A and B consist of permanent dikes. Project C is a small dam. The dam will have recreation and irrigation benefits as well as the flood control benefits. Facts about the three projects are shown in the following table. Each project has a life of 28 years. The MARR is 10 percent. First cost (millions of yuan) Annual benefits (millions of yuan) Annual operating and maintenance costs (millions of yuan) Complete parts (a) through (d) below. Project A 207 26.9 2.5 Project B 251 34.5 2.5 Project C 422 57.6 4.2 3 Click the icon to view the table of compound interest factors for discrete compounding periods when i = 10%. a. Use present worth to choose the best project. 1and Project is the best choice. The present worths in millions of yuan for projects A, B, and C, respectively, are (Round to two decimal places as needed.) b. Compute the benefit-cost ratios for the three projects. and The BCRs for projects A, B, and C, respectively, are (Round to three decimal places as needed.) c. Use incremental benefit-cost to choose the best project. BCR(B-A) is and BCR(C-B) is so project is the best choice. (Round to three decimal places as needed.) d. It is possible that the dam (project C) will cause some wildlife damage. This damage might be prevented by an additional expenditure of 23 million yuan when the dam is constructed. Does this change the choice of best project? Compute the benefit-cost ratio of project C assuming the extra 23 million yuan is an addition to the first cost. Use incremental benefit-cost to choose the best project. Vis the best choice. BCR(C) is and BCR(C-B) is so project (Round to three decimal places as needed.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Behavioral Finance And Asset Prices

Authors: David Bourghelle, Pascal Grandin, Fredj Jawadi, Philippe Rozin

1st Edition

3031244850, 978-3031244858

More Books

Students also viewed these Finance questions

Question

Write a Python program to check an input number is prime or not.

Answered: 1 week ago