the city of donville is planning to build a small 7 MW geothermal energy plant with an initial investment of $50 million and a life
the city of donville is planning to build a small 7 MW geothermal energy plant with an initial investment of $50 million and a life of 40 years. the city uses a rate of 6% per year compounded yearly. if the plant will be needed indefinetly, what is the total investment that the city should budget the project for?