The completion time of a construction project depends on whether the carpenters or the plumbers working on theproject go on strike. The probabilities of delay

The completion time of a construction project depends on whether the carpenters or the plumbers working on theproject go on strike. The probabilities of delay are 100%, 80%, 40%, and 5% if both go on strike, carpenters alonego on strike, plumbers alone go on strike, and neither of them strikes respectively. Also, there is 60% chance thatplumbers will strike if carpenters strike, and if plumbers go on strike there is a 30% chance that carpenters wouldfollow. It is known that the chance for the plumbers strike is 10%.

Determine the probability of delay in completion

If there is a delay in completion, determine the following:i) Probability that both carpenters and plumbers are on strike

.ii) Probability that carpenters strike and plumbers are not on strike.

iii) Probability that carpenters are on strike.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

An Introduction to the Mathematics of financial Derivatives

Authors: Salih N. Neftci

2nd Edition

978-0125153928, 9780080478647, 125153929, 978-0123846822

More Books

Students also viewed these Mathematics questions