The construction project is running behind schedule and over budget. To bring the project in on budget, which of the following is true of the
The construction project is running behind schedule and over budget.
To bring the project in on budget, which of the following is true of the TCPI?
The TCPI is greater than
The TCPI is less than
The TCPI is an index of how far off
The TCPI is negative