The cost baseline for a project is as follows: Month 1 2 3 4 5 Total Planned Expenditure $30,000 $30,000 $40,000 $50,000 $50,000 $200,000 At
The cost baseline for a project is as follows:
Month | 1 | 2 | 3 | 4 | 5 | Total |
Planned Expenditure | $30,000 | $30,000 | $40,000 | $50,000 | $50,000 | $200,000 |
At the end of the first month, the project manager finds that the actual expenditure is $25,000. She also estimates that the projects rate of performance to be 80%.
- How is the projects performance at the end of the first month, in terms of budget and schedule?
- Based on the performances at the end of the first month, re-estimate the budget and schedule for this project.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started