The crash time of an activity represents a . the normal time to complete an activity. b . the most pessimistic time to complete an
The crash time of an activity represents
a
the normal time to complete an activity.
b
the most pessimistic time to complete an activity
c
the most likely time to complete an activity
d
the shortened activity time
e
None of the above