Question
1 Approved Answer
The critical path for is the following network diagram is: Activity B 5 days Activity A Activity C 2 days 2 days Activity F 3
The critical path for is the following network diagram is: Activity B 5 days Activity A Activity C 2 days 2 days Activity F 3 days Activity D Activity E 3 days 1 days O Activity C, Activity E, Activity F Activity A, Activity B, Activity F O Activity A, Activity D, Activity E, Activity F O Activity A, Activity C, Activity F