The critical path of a project consists of activities A, B, C with the following duration estimates. Activity A: Optimistic = 5, Pessimistic = 9,
The critical path of a project consists of activities A, B, C with the following duration estimates.
Activity A: Optimistic = 5, Pessimistic = 9, Most Likely = 7;
Activity B: Optimistic = 8, Pessimistic = 14, Most Likely = 10;
Activity C: Optimistic = 4, Pessimistic = 7, Most Likely = 5.
What is the range of the estimated project duration?