The critical path on a project has 4 tasks, A , B , C , and D . The allowable amounts of crashing and the

The critical path on a project has 4 tasks, A, B, C, and D. The allowable amounts of crashing and the costs for crashing are given as
\table[[Task,Adays allowed,$$$ day,\table[[I of days],[Crashed]],Cost],[A,2,30,,],[B,3,50,,],[C,1,25,,],[D,2,15,,]]
DRAW:
To crash the project by 6 days,
A should be crashed by [blank1] days.
B should be crashed by [blank2] days.
Cshould be crashed by [blank3] days.
D should be crashed by [blank4] days.
The order of crashing these will be [blank5].
The total cost of crashing by 6 days will be[blank6].
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management

Authors: Richard Lynch

8th Edition

1292211407, 978-1292211404

More Books

Students also viewed these General Management questions

Question

1.) Graphically add the two vectors shown below.

Answered: 1 week ago