Question
The CyClon project team has started gathering information necessary to develop a project network-predecessor activities and activity time in days. The results of their meeting
The CyClon project team has started gathering information necessary to develop a project network-predecessor activities and activity time in days. The results of their meeting are found in Table 1.
(a) Complete the Microsoft Project Entry Table below based on the information given in Table 1.
(b) How long will the project take?
(c) What is the critical path for the project?
(d) Upon further review the team recognizes that they missed three finish-to-start lags.Procure prototype parts will involve only 2 days of work but it will take 8 days for the parts to be delivered. Likewise, Order stock components will take 2 days of work and 8 days for delivery and Order custom components 2 days of work and 13 days for delivery.
Reconfigure the Cyclon schedule by entering the three finish-to-start lags. What impact did these lags have on the original schedule, and on the amount of work required to complete the project?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started