Question
The demand for subassembly S is 150 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U.
The demand for subassembly S is
150
units in week 7. Each unit of S requires
1
unit
of T and
1
unit
of U. Each unit of T requires
2
units
of V,
2
units
of W, and
2
units
of X. Finally, each unit of U requires
2
units
of Y and
3
units of Z. One firm manufactures all items. It takes 2 weeks to make S,
1
week
to make T, 2 weeks to make U,
2
weeks
to make V,
3
weeks to make W,
1
week
to make X, 2 weeks to make Y, and
1
week
to make Z.
LOADING...
Click the icon to view the product structure and the time-phased product structure.
LOADING...
Click the icon to view the on-hand inventory.
Part 2
Construct a net material requirements plan using on-hand inventory
(enter
your responses as whole
numbers).
Week | Lead Time | ||||||||
Item | 1 | 2 | 3 | 4 | 5 | 6 | 7 | (weeks) | |
S | Gross req | enter your response here | 2 | ||||||
On hand | enter your response here | ||||||||
Net req | enter your response here | ||||||||
Order receipt | enter your response here | ||||||||
Order release | enter your response here |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started