The desired daily output for an assembly line is 300 units. This assembly line will operate 375 minutes per day. The following table contains information
The desired daily output for an assembly line is 300 units. This assembly line will operate 375 minutes per day. The following table contains information on this product's task times and precedence relationships:
TASK | TASK TIME (SECONDS) | IMMEDIATE PREDECESSOR |
A | 35 | |
B | 40 | A |
C | 20 | A |
D | 20 | C |
E | 50 | C |
F | 25 | B |
G | 35 | D-E |
H | 10 | F-G |
b.What is the workstation cycle time?
c. Balance this line using the largest number of following tasks. Use the longest task time as a secondary criterion. (Leave no cells blank - be certain to enter "0" wherever required.)
d. What is the efficiency of your line balance? (Round your answer to 1 decimal place.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started