Question
The Dopler Manufacturing Company has two production departments (Assembly and Finishing) and two service departments (Human Resources and Janitorial). The projected usage of the two
The Dopler Manufacturing Company has two production departments (Assembly and Finishing) and two service departments (Human Resources and Janitorial). The projected usage of the two service departments is as follows:
Use of | Use of | |
Human Resources | Janitorial | |
Human Resources | 10% | |
Janitorial | 10% | |
Assembly | 60% | 35% |
Finishing | 30% | 55% |
The budgeted costs in the service departments are: Human Resources, $90,000 and Janitorial, $60,000. rev: 10_29_2012
4.
value: 10.00 points
Required information
Using the step-down method and assuming the Human Resources Department is allocated first, the amount of Human Resources cost allocated to the Assembly Department is:
$60,000.
$96,567.
$36,667.
$54,000.
$23,333.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started