Question

1 Approved Answer

The Emerald Investment Group is considering investing in six projects. The expected net present value (NPV) and the required capital at the present time for

The Emerald Investment Group is considering investing in six projects. The expected net present value (NPV) and the required capital at the present time for each project are given in the table below.

Project Expected NPV ($) Required Capital ($)
1 6,000 5,000
2 8,000 7,000
3 3,000 2,000
4 5,000 4,000
5 7,000 6,000
6 4,000 3,000

At present, a budget of $21,000 is available for investment. Emerald has specific requirements for the investment, as detailed in the Constraints section given below.

Please help Emerald develop an investment plan by formulating an integer linear optimization model.

I. Define the decision variables.

(Note: This step is done for you. Please use these decision variables hereafter.)

X1 = 1 if project 1 is selected for investment; 0 otherwise.

X2 = 1 if project 2 is selected for investment; 0 otherwise.

X3 = 1 if project 3 is selected for investment; 0 otherwise.

X4 = 1 if project 4 is selected for investment; 0 otherwise.

X5 = 1 if project 5 is selected for investment; 0 otherwise.

X6 = 1 if project 6 is selected for investment; 0 otherwise.

II. Write the objective (mathematically).

Question A: What is the objective?

Question options:

Max Z = X1 + X2 + X3 + X4 + X5 + X6

Min Z = 6,000 X1 + 8,000 X2 + 3,000 X3 + 5,000 X4 + 7,000 X5 + 4,000 X6

Max Z = 5,000 X1 + 7,000 X2 + 2,000 X3 + 4,000 X4 + 6,000 X5 + 3,000 X6

Min Z = X1 + X2 + X3 + X4 + X5 + X6

Min Z = 5,000 X1 + 7,000 X2 + 2,000 X3 + 4,000 X4 + 6,000 X5 + 3,000 X6

Max Z = 6,000 X1 + 8,000 X2 + 3,000 X3 + 5,000 X4 + 7,000 X5 + 4,000 X6

III. Write the constraints (mathematically).

Question B: Among projects 1, 3, and 4, two of them must be selected.

Question options:

X1 + X3 + X4 2

X1 + X2 + X3 + X4 + X5 + X6 = 2

X1 + X3 + X4 > 2

X1 + X3 + X4 2

X1 + X3 + X4 < 2

X1 + X3 + X4 = 2

Question C: Constraint on the budget.

Question options:

5,000 X1 + 7,000 X2 + 2,000 X3 + 4,000 X4 + 6,000 X5 + 3,000 X6 21,000

5,000 X1 + 7,000 X2 + 2,000 X3 + 4,000 X4 + 6,000 X5 + 3,000 X6 < 21,000

6,000 X1 + 8,000 X2 + 3,000 X3 + 5,000 X4 + 7,000 X5 + 4,000 X6 21,000

6,000 X1 + 8,000 X2 + 3,000 X3 + 5,000 X4 + 7,000 X5 + 4,000 X6 21,000

5,000 X1 + 7,000 X2 + 2,000 X3 + 4,000 X4 + 6,000 X5 + 3,000 X6 = 21,000

5,000 X1 + 7,000 X2 + 2,000 X3 + 4,000 X4 + 6,000 X5 + 3,000 X6 > 21,000

6,000 X1 + 8,000 X2 + 3,000 X3 + 5,000 X4 + 7,000 X5 + 4,000 X6 = 21,000

5,000 X1 + 7,000 X2 + 2,000 X3 + 4,000 X4 + 6,000 X5 + 3,000 X6 21,000

Question D: If project 3 is selected, project 6 cannot be selected.

Question options:

X3 X6

X3 < X6

X3 + X6 1

X3 + X6 = 1

X3 + X6 1

X3 X6

X3 > X6

Question E: At least three projects must be selected.

Question options:

X1 + X2 + X3 + X4 + X5 + X6 = 3

X1 + X2 + X3 + X4 + X5 + X6 < 3

X1 + X2 + X3 + X4 + X5 + X6 3

X1 + X2 + X3 + X4 + X5 + X6 > 3

X1 + X2 + X3 + X4 + X5 + X6 3

Question F: If project 2 is selected, project 5 must be also selected.

Question options:

X2 < X5

X2 X5

X2 X5

X2 + X5 1

X2 + X5 1

X2 + X5 = 1

X2 > X5

Question G: At most five projects are to be selected.

Question options:

X1 + X2 + X3 + X4 + X5 + X6 5

X1 + X2 + X3 + X4 + X5 + X6 5

X1 + X2 + X3 + X4 + X5 + X6 = 5

X1 + X2 + X3 + X4 + X5 + X6 > 5

X1 + X2 + X3 + X4 + X5 + X6 < 5

Question H: Constraints on decision variables.

Question options:

X1, X2, X3, X4, X5, X6 0

X1 + X2 + X3 + X4 + X5 + X6 0

X1, X2, X3, X4, X5, X6 0 or 1

X1, X2, X3, X4, X5, X6 = 0 or 1

X1 + X2 + X3 + X4 + X5 + X6 1

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managing Supply Chain and Operations An Integrative Approach

Authors: Thomas Foster, Scott E. Sampson, Cynthia Wallin, Scott W Webb

1st edition

132832402, 978-0132832403

More Books

Students also viewed these General Management questions

Question

Explain about Schema refinement in Database design?

Answered: 1 week ago

Question

Illustrate Concurrent execution of transaction with examples?

Answered: 1 week ago

Question

Divide and rule ?

Answered: 1 week ago