Question

1 Approved Answer

The estimated duration of the pouring concrete activities in a commercial building project is 3 0 days. After 1 8 days, the project manager receives

The estimated duration of the pouring concrete activities in a commercial building project is 30 days. After 18 days, the project manager receives the following information
\table[[Activity,Total quantity (m3),Total budget,Actual quantity (m3),Actual cost],[A,20,000,800,000,15,000,750,000],[B,11,000,550,000,8,000,320,000],[C,9,000,180,000,3,000,75,000],[D,10,000,700,000,0,0]]
Find:
The actual percent completed for pouring concrete activity
(7%)
The BCWS and BCWP until the current date (day 18)
(5%)
The values of CPI and SPI
(2%)
The Estimated At Completion
(3%)
What is the anticipated actual cost of activity D
(4%)
What could be the total delay or schedule advantage for the project in days
(4%)
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: William J Stevenson

12th edition

2900078024107, 78024102, 978-0078024108

More Books

Students also viewed these General Management questions

Question

=+ Which are the most important performance measures?

Answered: 1 week ago