The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assume
The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assume that the activity times are independent.
Time (weeks) | Immediate | Time (weeks) | Immediate | ||||||||||||
Activity | a | m | b | Predecessor(s) | Activity | a | m | b | Predecessor(s) | ||||||
A | 7 | 10 | 12 | C | 7 | 10 | 11 | A | |||||||
B | 4 | 12 | 17 | D | 6 | 10 | 12 | B |
This exercise contains only parts a, b, c, d, and e.Part 2a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places):
Activity | Expected Time | Variance | |
A | 9.83 | . 69 |
Part 3
B | 11.5 | 4.69 |
Part 4
C | 9.66 | .44 |
Part 5
D | 9.66 | 1 |
Part 6b) The expected completion time of the critical path = _________
enter your response here in
weeks (round your response to two decimal places).
The variance of the critical path = ________ weeks.
The expected completion time of the path other than the critical path = ____________ weeks.
The variance of the path other than the critical path = ___________ weeks.
If the time to complete the activities on the critical path is normally distributed than the probability that the critical path will be finished in 21 weeks or less = __________
If the time to complete the activities on the critical path is normally distributed than the probability that the critical path will be finished in 23 weeks or less = __________
If the time to complete the activities on the non critical path is normally distributed, then the probability that the non critical path will be finished in 21 weeks or less = _____________
If the time to complete the activities on the non critical path is normally distributed, then the probability that the non critical path will be finished in 23 weeks or less = _____________
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started