Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assume

The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assume that the activity times are independent.
Time (weeks)
Immediate
Time (weeks)
Immediate
Activity
a
m
b
Predecessor(s)
Activity
a
m
b
Predecessor(s)
A
C
A
B
D
B
This exercise contains only parts a, b, c, d, and e.
Part 2
a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places):
Activity
Expected Time
Variance
A
9.66
0.44
Part 3
B
11.33
4
Part 4
C
9.66
0.44
Part 5
D
9.50
1.36
Part 6
b) The expected completion time of the critical path=
enter your response here weeks (round your response to two decimal places).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Project Management

Authors: Joseph Heagney

5th Edition

0814437362, 978-0814437360

More Books

Students also viewed these General Management questions

Question

=+b the discounted payback; c the net present value.

Answered: 1 week ago

Question

Did you offer hard data that is verifiable? [D]

Answered: 1 week ago