The factory overhead rate used to apply overhead cost to jobs is called a predetermined rate because it is calculated as follows: ( Note: For
The factory overhead rate used to apply overhead cost to jobs is called a predetermined rate because it is calculated as follows: Note: For purposes of the answers below, estimated means the same as budgeted.
estimated overhead divided by actual hours
estimated overhead divided by estimated hours
actual overhead divided by actual hours
actual overhead divided by estimated hours