Question
The faculty office area in the Antonio Lucchetti building has problems associated with the air conditioning system. Currently the existing system is centrifugal. The Department
The faculty office area in the Antonio Lucchetti building has problems associated with the air conditioning system. Currently the existing system is centrifugal. The Department of Buildings and Land is evaluating two alternatives to address the situation.
The first alternative is to replace the 50-ton chiller, the handler system and its insulating system.
The initial costs are as follows:
Unit | Cost | Life |
Centrifuge 50 tons | $33,000 | 15 years |
Handlers | $47,000 | 30 years |
Work for installation* | $1,400 | n/a |
Materials for initial installation ** | $2,500 | n/a |
Isolation system | $22,000 | n/a |
*Reduced to 40% of original cost in case of equipment replacement.
** The cost of replacement materials is also assumed to be 40% of the original cost.
The maintenance of the centrifuge consists of
Maintenance work | Personnel requirements | Duration of work | Monthly salary | Cost |
Cleaning every 6 months | 1 technician 1 helper | 1 day | $1,550 $1,515 | |
Annual water pump maintenance | 1 technician 1 helper | 1/2 day | $1,550 $1,515 | |
Annual manufacturer's visit | $1,000 | |||
I replace fans every three years | 1 technician 1 helper | 1 hour | $1,550 $1,515 | $150 |
The maintenance is carried out by staff of the Refrigeration Workshop attached to the Department of Buildings and Land of the land. The total number of hours a regular employee works in the Campus is 1,950 hours per year, at a rate of 7.5 hours per day. (You must calculate the cost associated with the time that staff spendon the maintenance of these particular equipment.)
The additional costs associated with the operation of the centrifuge are as follows
Cost item | Frequency | Cost |
Replacing cold water pipe isolated | Every 6 years | $22,000 |
The costs associated with electricity consumption to the centrifuge system are as follows:
-
The daily electricity consumption cost of a 50-ton centrifuge is$150 per day.
-
The cost for electric consumption of the handle is $25 a day.
The centrifuge system operates continuously.
The second alternative is the installation of a system of individual units consisting of four capacitors and 41 consoles.
The initial costs are as follows:
Cost item | Unit cost | Units | Total cost | Life |
Condenser MDV 400 | $9,000 | 2 | 6 years old | |
Condenser MDV 450 | $9,700 | 2 | 6 years old | |
Consoles 12,000 BTU | $700 | 31 | 6 years old | |
Consoles 19,000 BTU | $900 | 10 | 6 years old | |
Materials*** | $35,000 | n/a | ||
Work for installation**** | $18,000 | n/a |
***Includes materials for the insulation system. The cost of materials for the replacement of the consoles is obvious.
****Replacement work is reduced to 80% of the original cost..
System maintenance consists of
Maintenance work | Personnel requirements | Units | Duration of work | Monthly salary | Cost parts to replace |
Console cleaning and filter replacement once a year | 1 technician 1 helper | 41 | 1.5 hours | $1,550 $1,515 | $30/unit |
Condenser cleaning once a year | 1 technician 1 helper | 4 | 1 hour | $1,550 $1,515 | |
Replacement console removal pump, every 3 years | 1 technician 1 helper | 41 | 1/4 day | 1 technician 1 helper | $50/unit |
The maintenance is carried out by staff of the Refrigeration Workshop Attached To the Department of Buildings and Land of the land. The total number of hours a regular employee works in the Campus is 1,950 hours per year, at a rate of 7.5 hours per day. (You must calculate the cost associated with the time staff spend on the maintenance of these particular equipment.)
The additional costs associated with operating the console system are as follows
Cost item | Frequency | Cost |
Refrigerant pipe insulation replacement | Every 12 years | $12,000 |
The costs associated with console system power consumption are as follows:
-
The cost for electricity consumption of the complete console system is$175 per day, at the rate of 12 hours per day.
Presumes that the system will operate for 260 working days annually.
(Problem starts below)
-
Realize a sensitivity analysis, keeping the parameters of the centrifuge system constant, and changing the life of the console system from 5 years to a maximum of 10 years.
--Hi, I know its long. What I need to understand is what's marked in bold. Please write neatly and use all the information NEEDED to answer/explain what is in bold. I want to learn so that I can be able to do this with different exercises. -- any suggestion and/ or more info needed just let me know in the comments. Completely opened. Thank you in advance.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started