Question
1 Approved Answer
The Farm - 4 - Less tractor company produces a grain combine ( GC ) in addition to both a large ( LT ) and
The FarmLess tractor company produces a grain combine GC in addition to both a large LT and small size tractor SM Its production manager desires to produce to customer demand using a mixed model production line. The current sequence of production, which is repeated times during a shift, is:
SMGCLTSMGCLTSMGCLTSM
A new machine is produced every minutes. The plant operates two eighthour shifts. There is no downtime because the fourhours between each shift are dedicated to maintenance and restocking raw material. Based on this information, answer the following questions.
a How long does it take the production cycle to be completed?
The cycle sequence is completedin minutes. Enter your response as a whole number.
b How many of each type of machine does FarmLess produce in a shift? Enter your responses as
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started