The fire department expected to spend $100,000 in April. Actually, it spent $108,680. The department thought it would pay each member of its team of
The fire department expected to spend $100,000 in April. Actually, it spent $108,680. The department thought it would pay each member of its team of firefighters $25 per hour. However, it paid them each $26 per hour on average. The department expected that the team of firefighters would work a total of 4,000 hours and fight 100 fires. Of course, many hours the firefighters are on duty in the station house between fires. Those hours are considered to be worked and the firefighters are paid for those hours. The actual results were 4,180 hours worked by the team of firefighters and 110 fires fought by the department.
A. What was the total variance? (4 points) B. What were the rate (or price). quantity, and volume variances? (3 points) C. Which variances were favorable and which were unfavorable? (3 points) Total Variance $100 Original Budget: Budgeted Volume X Budgeted Quantity x Budgeted Rate Flex Budget: Actual Volume x Budgeted Quantity X Budgeted Rate X X Volume Variance Flex Budget: Actual Volume X Budgeted Quantity X Budgeted Rate VQA Budget: Actual Volume X Actual Quantity X Budgeted Rate X X Quantity Variance VQA Budget: Actual Volume x Actual Quantity x Budgeted Rate Actual: Actual Volume x Actual Quantity x Actual Rate X X Price Variance Volume variance Quantity Variance Price Variance Total VarianceStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started