The first unit required 10,000 hours to manufacture. The company expects to experience an 88% unit learning curve. Estimate the hours of the 19th unit.
The first unit required 10,000 hours to manufacture. The company expects to experience an 88% unit learning curve. Estimate the hours of the 19th unit. (Round intermediate calculations to 4 decimal places)
4,855 hours |
5,810 hours |
5,640 hours |
1,345 hours |