The following 6 jobs are scheduled through a machine repair shop (repair times are shown in days). What is the flow time for customer A if an SPT (shortest Processing Time) sequence is used? Customer Time Since Order Arrived (days ago) Repair Time Due Date (days from now) A 10 5 11 B 7 3 9 C 5 7 10 D 5 8 8 E 6 4 7 F 8 6 6 Group of answer choices 13 22 26 18 27