The following 6 months of data were collected on electricity cost and the number of machine hours in a factory. Electricity Machine Month cost hours
The following 6 months of data were collected on electricity cost and the number of machine hours in a factory.
Electricity | Machine | |
Month | cost | hours |
June | $25,160 | 4,500 |
July | 26,170 | 4,810 |
August | 27,250 | 5,120 |
September | 26,680 | 5,010 |
October | 27,950 | 5,430 |
November | 27,500 | 5,190 |
Refer to Figure 3-13. A dependent variable value used in calculating the cost line using the high-low method is:
a. | 5,430 | |
b. | $27,900 | |
c. | 4,500 | |
d. | $25,160 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started