The following activities are part of a project to be scheduled using CPM:
\table[[ACTIVITY,IMMEDIATE PREDECESSOR,TIME (WEEKS)],[A,-,6],[B,A,3],[c,A,7],[D,c,2],[E,B, D,4],[F,D,3],[G,E,F,7]]
b. What is the critical path?
A-C-D-E-G
A-C-D-F-G
A-B-E-G
c. How many weeks will it take to complete the project?
Number of weeks
d. How much slack does activity B have?
Slack of activity B
weeks
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Processes and Supply Chains

Authors: Lee J. Krajewski, Larry P. Ritzman, Manoj K. Malhotra

10th edition

978-013280747, 132807394, 9780132951814, 132807475, 132951819, 978-0132807395

More Books

Students also viewed these General Management questions

Question

1. Identify and explain the three key dimensions of motivation.

Answered: 1 week ago