The following activities are part of a project to be scheduled using CPM: table [ [ ACTIVITY , IMMEDIATE PREDECESSOR,TIME ( WEEKS ) ]

The following activities are part of a project to be scheduled using CPM:
\table[[ACTIVITY,IMMEDIATE PREDECESSOR,TIME (WEEKS)],[A,-,8],[B,A,5],[C,A,9],[D,C,6],[E,B,D,4],[F,D,7],[G,E,F,4]]
b. What is the critical path?
A-B-D-F-G
A-C-D-E-G
A-C-D-F-G
A-B-E-G
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Chuck Williams

4th Edition

978-0324316797, 0324316798

More Books

Students also viewed these General Management questions